My house — Kigamboni
2 of 7 stages approved
TZS 200,000,000 build
Building stages
1
Site clearing and setting out
TZS 8,000,000
Approved
2
Foundation
TZS 30,000,000
Approved
4
Roof
TZS 35,000,000
Upcoming
5
Plumbing and electrical
TZS 28,000,000
Upcoming
6
Plastering and floors
TZS 30,000,000
Upcoming
7
Finishing and handover
TZS 29,000,000
Upcoming
Walls are ready for your check
Photos, video and receipts from Amina Juma, Oweru checker.
Review stage 3Paid to builder
TZS 40M
Waiting for you
TZS 40M
Still to come
TZS 120M
Your team
B
Bora Construction Ltd
Building Company · CRB registered
C
Amina Juma
Oweru checker · not the builder
O
Fatuma Msangi
Oweru project manager · your single point of contact