Build a three-bedroom house
Be the first to apply. No one has sent a proposal yet, so yours gets seen first.
Why take this job
You earn TZS 10,000 for assessing the site
Released per milestone once the client confirms the work
About the job
I want to build a three bedroom house 1. House drawings and building permit (Architect + structural engineer, about 4 weeks) 2. Site clearing, setting out and foundation (Mason + steel fixer, about 3 weeks) 3. Walls, columns and ring beam (Mason + steel fixer, about 5 weeks) 4. Roof structure and iron sheets (Carpenter + roofer, about 3 weeks) 5. Electrical wiring and plumbing pipework (Electrician + plumber, about 2 weeks) 6. Plastering, windows and doors (Mason + window and door fitter, about 4 weeks) 7. Gypsum ceilings (Gypsum specialist, about 2 weeks) 8. Floor and bathroom wall tiles (Tiler, about 2 weeks) 9. Painting, sanitary fittings and final fix (Painter + plumber + electrician, about 2 weeks)