Stage 3 · Walls up to the ring beam
Checked by Amina Juma, Oweru checker · Kigamboni · 6 Nov 2026
Recorded by the checker on site · place and date stamped
Photo · front wall
Kigamboni · 6 Nov 2026
Photo · back wall
Kigamboni · 6 Nov 2026
Photo · ring beam
Kigamboni · 6 Nov 2026
Done
Walls are built to the agreed height and specification. Ring beam is poured and cured. No cracks, formwork removed cleanly. Ready for the roof stage.
Release to builder
TZS
40,000,000
40,000,000
Oweru fee for this stage
TZS 1,920,000
Approve and release
No answer in 3 days? The money is released automatically.